Furnish and install new medium pressure and low pressure duct on floors 3 and 4, half of floor 1. The project called for 134 new VAV boxes and 250 Grilles and registers along with 2100 feet of linear diffusers, 137 diffuser plenum’s with remote cable operated dampers. The challenge on this project was the aggressive 5 month schedule to complete the project in 6 months including demolition, construction of walls and finishes. Meaning we had about 12 weeks to demolish, fabricate about 40,000 lbs of duct and install that plus the equipment listed above. The project came in on time and budget and DJ Wagner was awarded the rest of the building in phases as they became available.