Project Name: Sisters of Saint Joseph Novitiate
Owner: Chestnut Hill College
Project Client: Arch Diocese of Philadelphia
Construction Manager/ GC: Wohlsen Construction
Architect: Bruce E. Brooks & Associates
Engineer: Bruce E. Brooks & Associates
Project Schedule: November 2012 to April 2014
Summary of Scope and Project:
DJ Wagner’s installed new HVAC into an existing convent originally built as a private mansion in 1849. Running duct and pipe throughout including an existing tunnel that looked like a secret passageway from years past. Paired with Wohlsen Construction, the project was completed on time and on budget.